Influence, of time randomness execution of work, on lenght of the construction cycle
Wariant tytułu
Wpływ losowości czasów wykonywania robót na długość cyklu budowy
Autor
Więckowski, Andrzej
Opublikowane w
Technical Transactions
Numeracja
Y. 114, vol. 3
Strony
115-123
Data wydania
2017
Miejsce wydania
Kraków
Wydawca
Wydawnictwo PK
Język
angielski
DOI
10.4467/2353737XCT.17.036.6347
Słowa kluczowe
time reserves, random processes, construction cycle
bufory czasowe, procesy losowe, cykl zadania
Abstrakt
The objective of this paper is to analyse the time reserves in scheduling periods for conducting processes that ensure construction deadlines can be met. By using the probability account and numerical analyses methods, including ‘Monte Carlo’, execution cycles have been analysed, as well as summary stoppage times for executing teams and working areas. On the basis of calculations made using data from studies made during the construction office building in Krakow it was stated that in order to keep to the planned deadline, must be smaller periods of performance of works by individual brigades, an average of 0,103 times of rhythm.
Celem jest analiza buforów czasu gwarantujących dotrzymanie planowanego terminu realizacji zadania. Z wykorzystaniem rachunku prawdopodobieństwa i metod analiz numerycznych, w tym „Monte Carlo”, zbadano okresy cykli realizacji zadań oraz sumaryczne czasy przestojów brygad wykonawczych i działek roboczych (frontów pracy). Na podstawie obliczeń danych z budowy biurowca w Krakowie stwierdzono, że dla zachowania planowanego terminu realizacji zadania, konieczne były mniejsze okresy wykonywania robót przez poszczególne brygady, średnio o 0,103 czasu trwania rytmu.
Klasyfikacja PKT
630000 Budownictwo
Wydział
Zbiory cyfrowe BPK
Licencja
Licencja PK
Prawa dostępu
Zasób dostępny dla wszystkich
Na stronie wykorzystywane są pliki cookie, bądź podobne rozwiązania. Aby poznać szczegóły zapoznaj się z polityką prywatności.